Keeley Construction installed the structural steel pipe racks, process and utility piping, and set all the equipment for a greenfield RNG facility. Once completed, this facility turned landfill gas into pipeline spec Renewable Natural Gas. Piping consisted of both carbon steel and stainless steel from ½” to 24”. The project was located in Manassas, Virginia and was completed on schedule. The project duration was 10 months of construction, with the overall peak manpower at approximately 40 craftspeople.