A white background with a few lines on it

Keeley Industrial Spotlight: Meigs County Primary Systems Operation Center

Georgetown, TN | New Construction | 147 Acres | 2023


The Keeley Construction Industrial team was called upon by the Tennessee Valley Authority (TVA) for a Design, Bid, Build phased scope of work at their Meigs County Primary Systems Operation Center in Georgetown, TN. Keeley Industrial was trusted with the fabrication and erection of structural steel and miscellaneous steel for the project.


Prior to construction, the overall site was a 147-acre greenfield. Across this 147-acre property, Keeley Construction erected six different structures:


·Systems Operations Center | Two-story structure with a 75,500 SF footprint

·Technical Support Building | Two-story structure with a 26,200 SF footprint

·Mechanical Yard C-1 & C-2 | Structure with a 18,500 SF footprint

·Mechanical Yard C-3 | Structure with a 6,000 SF footprint

·Receiving & Maintenance Building | Structure with a 7,200 SF footprint

·Security Building | Structure with a 1,500 SF footprint



Phase One of the project included the erection of the Systems Operations Center from February 2021 through May 2021. The five remaining structures were erected during Phase Two which began in April 2022 and ran through February 2023. Throughout both phases, Keeley Construction self-performed 27,600 manhours and utilized 1,600 tons of steel. 100% of the structural steel and miscellaneous steel erection was self-performed by Keeley and 704 local ironworkers, providing the team with control over the schedule, safety, and quality of the project.


Though completed successfully and to the full satisfaction of the client, there were a few challenges faced on this project. This particular area of Tennessee receives an average of 70 inches of rain per year, making some aspects of the project difficult as a majority of the work was done outside. However, Keeley Construction didn’t let the rain stop them as the project was completed on time. Construction of the Systems Operating Center utilized structural steel with a tilt up concrete panel construction around the perimeter. With the Technical Support Building and Mechanical Yards C-1, C-2, and C-3 adjacent to the Systems Operating Center by a 1-1/2” gap, installation challenges arose. Through innovative solutions, the Keeley team was able to access the anchor bolts and structural bolts in order to torque properly. Finally, within the Systems Operating Center, there was a control room that required 124’ long x 9’ deep trusses. Due to the length and logistics, each truss was sent to the jobsite in three sections. Keeley was able to pre-assemble the trusses onside prior to perfectly setting in place.


Keeley Industrial was able to complete the project on-time, on-budget, and with ZERO safety incidents!


“I don’t ever have to worry about Keeley not abiding by the safety guidelines on a project.”

-Project Partner

A woman with long dark hair and earrings is smiling for the camera.
By Claire Sauer September 12, 2024
Keeley Construction has offices across the nation, and as we expand our reach from coast to coast, we need dedicated Keeley’ns who are...
A collage of three pictures of a construction site with a bulldozer in the background.
By Claire Sauer September 6, 2024
New Construction | Aurora, CO | October 2024   Keeley Civil Energy has built a deep portfolio of partnerships and substation experience....
A collage of four pictures of a park with signs.
By Claire Sauer September 3, 2024
Restoration & New Construction | Eight Acres | St. Louis, MO | April 2024   Keeley Construction has proudly built relationships across...
A woman is smiling for the camera in front of a window.
By Admin August 5, 2024
Our craftspeople are at the heart and soul of Keeley Construction and our growth would not be possible without their hard work and...
A man in a suit and plaid shirt is smiling for the camera.
By Claire Sauer July 10, 2024
Our Civil Infrastructure team is made up of talented Keeley’ns that share a common goal – exceed expectations on every project for every...
By Claire Sauer July 9, 2024
Renovation | 22,000 SF | St. Louis, MO | March 2024 Keeley Construction’s Building Group and Financial Facilities Team proudly partner...
A collage of pictures of construction workers working on a building.
By Claire Sauer July 1, 2024
Keeley Construction proudly provides innovative solutions across our four business groups: Civil, Paving, Building, and Industrial....
A collage of four pictures of a grocery store.
By Claire Sauer May 16, 2024
New Construction | 28,000 SF | Sullivan, MO | October 2023 The Keeley Construction Building Group was called upon by Schnucks for the...
A man in a suit and white shirt is smiling in front of a window.
By Claire Sauer May 14, 2024
Keeley Construction serves as a true builder, enhancing and building up our communities across the nation. These endeavors could not...
A man in a blue shirt is smiling for the camera.
By Claire Sauer May 10, 2024
Our Keeley’ns in the Building Group passionately serve our customers by exceeding expectations on every project. With team members across...
More Posts
Share by: